Stage 9 Construction Updates

  • Construction Updates

Seventh Bend

09/12/2021

We look forward to keeping you up to date with the latest information on Stage 9 at Seventh Bend.
Construction is now underway and we are still anticipating titles on these lots in Q2 2022, as scheduled.

Please follow us on Facebook for project information and updates.


November/December ’21: Construction Update

– Road pavement construction ongoing.
– Footpath and vehicle crossover construction commenced.


October ’21: Construction Update

– Kerb construction has commenced
– Drainage infrastructure works are ongoing


September ’21: Construction Update

– Sewer infrastructure works have now been completed
– Drainage infrastructure works are ongoing
– Road boxing has commenced


August ’21: Construction Update

– Sewer infrastructure and bulk earthworks ongoing.
– Drainage infrastructure works commenced.


July ’21: Construction Update

– Bulk Earthworks have now commenced
– Civil works are expected to commence by the end of the month


June ’21: Construction Update

– Council engineering approval has now been received, and the Project Team is currently finalising the award of the works to a civil contractor
– Works are forecast to commence in early July