Stage 9 Construction Updates

  • Construction Updates

Seventh Bend

20/08/2021

We look forward to keeping you up to date with the latest information on Stage 9 at Seventh Bend.
Construction is now underway and we are still anticipating titles on these lots in mid-2022, as scheduled.

Please follow us on Facebook for project information and updates.


August ’21: Construction Update

– Sewer infrastructure and bulk earthworks ongoing.
– Drainage infrastructure works commenced.


July ’21: Construction Update

– Bulk Earthworks have now commenced
– Civil works are expected to commence by the end of the month


June ’21: Construction Update

– Council engineering approval has now been received, and the Project Team is currently finalising the award of the works to a civil contractor
– Works are forecast to commence in early July