Stage 17 Construction Updates
- Construction Updates
We look forward to keeping you up to date with the latest information on Stage 17 at Seventh Bend.
Construction is progressing and these lots are now titled!
Please follow us on Facebook for project information and updates
October ’22: Construction Update
– Authority compliance approvals are still underway, expecting approvals over the coming weeks.
– Council PC Achieved.
September ’22: Construction Update
– Council PC inspection has been completed
– Authority compliance approvals are underway
August ’22: Construction Update
– Concrete footpath works continue
– Topsoiling is now ongoing
July ’22: Construction Update
– Concrete footpath works and topsoiling is now underway
June ’22: Construction Update
– Electrical & NBN cabling underway
– Concrete footpath works have commenced
May ’22: Construction Update
– Electrical trenching is now underway
– Rock retaining wall construction commenced
April ’22: Construction Update
– Rock retaining wall construction has commenced
– Footpath construction underway
March ’22: Construction Update
– Drainage works underway
– Pavement works underway