Construction Update April 2026

10/04/2026

We are pleased to share the latest construction progress across the community, with civil works continuing to advance across multiple stages.

 

Stage 20

  • Drainage within the road reserve and capping layer have been completed.

  • Sub-base pavement and kerb and channel works are currently underway and continuing to progress.

Stage 21

  • Drainage, capping layer and kerb and channel works have been completed.

  • Base pavement works are now underway and continuing to progress.

Stage 15B

  • Drainage, capping layer and kerb and channel works are complete.

  • Base pavement works are currently underway and continuing to progress.

Toolern Creek

  • Stripping and earthworks have been completed.

  • Concreting of the shared path is now underway and continuing to progress.