Construction Update April 2026
We are pleased to share the latest construction progress across the community, with civil works continuing to advance across multiple stages.
Stage 20
-
Drainage within the road reserve and capping layer have been completed.
-
Sub-base pavement and kerb and channel works are currently underway and continuing to progress.
Stage 21
-
Drainage, capping layer and kerb and channel works have been completed.
-
Base pavement works are now underway and continuing to progress.
Stage 15B
-
Drainage, capping layer and kerb and channel works are complete.
-
Base pavement works are currently underway and continuing to progress.
Toolern Creek
-
Stripping and earthworks have been completed.
-
Concreting of the shared path is now underway and continuing to progress.