Posted on April 30, 2019
April Construction Update
April Construction Update
Stage 1 and 2:
All internal civil works on Stages 1 and 2 are now complete, though there are still some works continuing on the Exford Road/Conservation Avenue intersection.
Compliance approvals are now being sought from the relevant authorities, with settlements anticipated to occur in June.
We've prepared a Seventh Bend Purchaser Guide which can assist in preparing you for settlement and building your new home.
Stage 3 and 4:
Stage 3: Electrical installation within Stage 3 is now underway. Stage 3 is expected to title in July 2019
Stage 4: Electrical installation will commence shortly on Stage 4. Titles for Stage 4 are expected in August 2019.
Stage 5:
Stage 5A: Kerb and channel work underway in preparation for electrical installation, which will follow on from installation in Stage 4. Titles for Stage 5A are expected in August 2019.
Stage 5B: Road crossing conduits with Stage 5B are nearly complete, with kerb and electrical install to follow once completed in Stage 5A. Titles are expected in September 2019.
Stage 6:
Stages 6A: Electrical & water work will commence shortly, with road works to be constructed with Stage 4. Titles are expected in August 2019.
Stages 6B: Work on the sewer is continuing, with construction approximately 95% complete. Titles are expected in Q4 2019.
Stage 6C: With bulk earthworks complete, work on drainage has progressed, with work now 80% complete. Titles are expected in late Q4 2019/ Q1 2020.
Stage 6D: The next major construction milestone is the commencement of the sewer, which will begin once sewer work in Stage 6 and Stage 6B is finished. Titles are expected in late Q4 2019/ Q1 2020.