CONSTRUCTION UPDATES

Posted on April 30, 2019

April Construction Update

April Construction Update

Stage 1 and 2:

All internal civil works on Stages 1 and 2 are now complete, though there are still some works continuing on the Exford Road/Conservation Avenue intersection.

Compliance approvals are now being sought from the relevant authorities, with settlements anticipated to occur in June.

We've prepared a Seventh Bend Purchaser Guide which can assist in preparing you for settlement and building your new home.


Stage 3 and 4:

Stage 3: Electrical installation within Stage 3 is now underway. Stage 3 is expected to title in July 2019

Stage 4: Electrical installation will commence shortly on Stage 4. Titles for Stage 4 are expected in August 2019.


Stage 5:

Stage 5A: Kerb and channel work underway in preparation for electrical installation, which will follow on from installation in Stage 4. Titles for Stage 5A are expected in August 2019.

Stage 5B: Road crossing conduits with Stage 5B are nearly complete, with kerb and electrical install to follow once completed in Stage 5A. Titles are expected in September 2019.


Stage 6:

Stages 6A: Electrical & water work will commence shortly, with road works to be constructed with Stage 4. Titles are expected in August 2019.

Stages 6B: Work on the sewer is continuing, with construction approximately 95% complete. Titles are expected in Q4 2019.

Stage 6C: With bulk earthworks complete, work on drainage has progressed, with work now 80% complete. Titles are expected in late Q4 2019/ Q1 2020.

Stage 6D: The next major construction milestone is the commencement of the sewer, which will begin once sewer work in Stage 6 and Stage 6B is finished. Titles are expected in late Q4 2019/ Q1 2020.

Posted on April 03, 2019

Construction Update - March

Stage 1 and 2

Since the last update, delays have been encountered as a result of the external gas main, which provides gas to the estate. There were issues between the Gas Authority and their contractor, but we are pleased to advise that this has now been resolved and construction works are continuing to progress on the Conservation Avenue/Exford Road intersection.

Internal works for both stages are all but complete, with just sign and line marking remaining. Arrangements are being made for testing by the relevant authorities, in order to achieve Statement of Compliance.

Unfortunately though, as a result of the gas main issue, titles will be delayed. We now anticipate that title registration and settlement  will occur in June. 

Stages 3, 4 and 6A

Stage 3: Drainage wand work on the water main is now complete. Work on the kerbs is underway, with electrical installation commencing in April.

Stage 4 and Stage 6A: Work on the road crossings has commenced and is continuing over the course of the coming weeks.  Electrical work will commence in April, along with Kerb and Channel.

Stage 5

Stage 5A: Drainage work within the stage is now complete with work now commencing on the installation of the road crossings.

Stage 5B: The roads within the stage are now boxed with the next major milestone for the stage, work on the water main, commencing in April.

Stage 6B, 6C and 6D

Stages 6B: Work on the sewer is continuing, with construction approximately 50% complete.

Stage 6C & 6D: With bulk earthworks complete, the next major construction milestone is the commencement of the sewer, which will begin once sewer work in stage 6B is finished.

Posted on January 29, 2019

January 2019 Construction Update

Stage 1 and 2

Top soiling has commenced of the naturestrips and lots in stages 1 and 2. Concreting of footpaths is complete and the internal electrical works complete, with asphalt to be laid in the coming weeks.
With stage construction works still on track, it's estimated that titles will be received early April 2019*. 

Stages 3 and 4

Drainage works are still continuing on site, with drainage work around the roads 99% complete and works around the easements 20% complete in Stage 3 and drainage 70% complete in Stage 4.
Work on the watermain has now commenced.
With construction progressing well,  we estimate the construction process to be complete in Q2 2019 for Stage 3 and Q3 2019 for Stage 4.*  

Stages 5A and 5B

Sewer work is complete with earthworks continuing. 

Stage 6

Stage 6A: Sewer work is now complete with 70% of the drainage work complete.
Stages 6B, 6C & 6D: Bulk earthworks are now complete, with construction now focusing on essential services.

Posted on November 26, 2018

November Construction Update

Stage 1 and 2

NBN has been installed and concreting preparation for the footpaths has commenced.
Kerbing is complete, with asphalt expected to be laid in the new year.
We estimate that stage construction works are still on track issue titles late Q1/early Q2 2019*. 

Stages 3 and 4

Drainage works are still continuing. 
Road boxing is due to commence early December for Stage 3.
With construction progressing well,  we estimate the construction process to be complete in Q2 - Q3 2019*.  

Stages 5, 6A, B, C and D

Sewer work is complete in stages 5 and 6A with work continuing on drainage.
Preliminary earthworks for Stage 6B, 6C and 6D have commenced, with bulk earthworks commencing next week.

Posted on November 12, 2018

October Construction Update

Stage 1 and 2

All essential services have now been installed with the electrical installation underway. 

Kerbing has now been completed.

We estimate that stage construction works will be completed in the first quarter of 2019. Once construction works are complete, all services are then audited before being accepted by the local authorities and Statement of Compliance "SOC" being issued.

Stages 3, 4 & 5

The installation of the sewer is now complete.

Installation of drainage for Stages 3 & 4 is in progress. 

With construction now underway we estimate that the construction process to be complete in Q2 - Q3 2019. Please note that this timing is provided as a guideline only. Construction timelines are subject to many variables and environmental factors.

Posted on September 14, 2018

SEPTEMBER CONSTRUCTION UPDATE

Stage 1 and 2

All essential services have now been installed below ground and the roads are beginning to take shape. From here, footpaths and driveways will be installed as the stage transforms into your new address.

We estimate that stage construction works will be completed in the first quarter of 2019. Once construction works are complete, all services are then audited before being accepted by the local authorities and Statement of Compliance "SOC" being issued.

Stages 3, 4 & 5

Construction commenced in early August with majority of the earthworks now complete. Installation of drainage pits and pipes are also complete with works progressing well on installation of the sewer.

With construction now underway we estimate that the construction process to be complete in Q2 - Q3 2019.

Please note that this timing is provided as a guideline only. Construction timelines are subject to many variables and environmental factors such as weather, that can cause delays however we will provide regular construction updates, along the way so you can prepare for settlement

Follow Seventh Bend on Facebook to find out more about what's happening in your new community!

CALL 0418 577 055 TO SPEAK TO A CONSULTANT

Contact Us
Seventh Bend Sales Team
Phone: 0418 577 055
Email: seventhbend@latituderealestate.com.au

Seventh Bend Sales Office
180 - 238 Exford Road,
Weir Views, Vic 3338
Open 7 days 11am - 5pm

Connect With Us