CONSTRUCTION UPDATES

Posted on November 26, 2018

November Construction Update

Stage 1 and 2

NBN has been installed and concreting preparation for the footpaths has commenced.
Kerbing is complete, with asphalt expected to be laid in the new year.
We estimate that stage construction works are still on track issue titles late Q1/early Q2 2019*. 

Stages 3 and 4

Drainage works are still continuing. 
Road boxing is due to commence early December for Stage 3.
With construction progressing well,  we estimate the construction process to be complete in Q2 - Q3 2019*.  

Stages 5, 6A, B, C and D

Sewer work is complete in stages 5 and 6A with work continuing on drainage.
Preliminary earthworks for Stage 6B, 6C and 6D have commenced, with bulk earthworks commencing next week.

Posted on November 12, 2018

October Construction Update

Stage 1 and 2

All essential services have now been installed with the electrical installation underway. 

Kerbing has now been completed.

We estimate that stage construction works will be completed in the first quarter of 2019. Once construction works are complete, all services are then audited before being accepted by the local authorities and Statement of Compliance "SOC" being issued.

Stages 3, 4 & 5

The installation of the sewer is now complete.

Installation of drainage for Stages 3 & 4 is in progress. 

With construction now underway we estimate that the construction process to be complete in Q2 - Q3 2019. Please note that this timing is provided as a guideline only. Construction timelines are subject to many variables and environmental factors.

Posted on September 14, 2018

SEPTEMBER CONSTRUCTION UPDATE

Stage 1 and 2

All essential services have now been installed below ground and the roads are beginning to take shape. From here, footpaths and driveways will be installed as the stage transforms into your new address.

We estimate that stage construction works will be completed in the first quarter of 2019. Once construction works are complete, all services are then audited before being accepted by the local authorities and Statement of Compliance "SOC" being issued.

Stages 3, 4 & 5

Construction commenced in early August with majority of the earthworks now complete. Installation of drainage pits and pipes are also complete with works progressing well on installation of the sewer.

With construction now underway we estimate that the construction process to be complete in Q2 - Q3 2019.

Please note that this timing is provided as a guideline only. Construction timelines are subject to many variables and environmental factors such as weather, that can cause delays however we will provide regular construction updates, along the way so you can prepare for settlement

Follow Seventh Bend on Facebook to find out more about what's happening in your new community!

CALL 0418 577 055 TO SPEAK TO A CONSULTANT

Contact Us
Maria Abalos
Phone: 0418 577 055
Email: seventhbend@latituderealestate.com.au

Seventh Bend Sales Office
180 - 238 Exford Road,
Weir Views, Vic 3338
Open 7 days 11am - 5pm

Connect With Us